No Delays at Paks
Subscribe to the newsletter
Select the region you are interested in and enter your e-mail
Subscribe
#158December 2016

No Delays at Paks

back to contents

According to him, the in-depth research effort involved the use of the most advanced instrumentation to validate the suitability of the site for a new power plant and there are no factors that might prevent its construction. Speaking of the project schedule, the government’s commissioner stressed that, although the licensing process did not affect the time schedule, further work would require approval of Hungary’s nuclear regulator. Mr. Aszódi emphasized that Hungary was expecting the European Commission to make its final decision on the government support for the project. “A clear time schedule can only be established after this decision is taken”, Aszódi explained. “I cannot tell you how the EC decision will influence the project implementation until we finally get the decision. It may contain requirements that will impact the construction schedule,” he added.