Construction sites. Rosatom accomplished a unique task of shipping heavy equipment from Saint Petersburg to the Akkuyu NPP construction site in Turkey. Escorted by three icebreakers on the frozen Neva River, two tugboats towed barges carrying two horizontal moisture separator reheaters (MSRs) for Akkuyu Unit 1. The drawbridges over the Neva were raised to let the convoy pass, which is uncommon in winter. The total weight of the equipment is 640 tonnes. Each reheater is 22.3 meters long. The moisture separator reheaters for the Turkish nuclear power plant are the first in Russia to have been made horizontal. This design improves performance of the turbines, with only two MSRs used instead of four. The Akkuyu Nuclear Power Plant comprises four power units with a total installed capacity of 4,800 MW.