Foundation Completed
Subscribe to the newsletter
Select the region you are interested in and enter your e-mail
Subscribe
#205May 2018

Foundation Completed

back to contents

“The work is proceeding on schedule. Our next major step is to erect containment walls,” said ASE Senior Vice President Alexander Khazin.

Shawkat Akbar, Director of the Rooppur Project on the part of Bangladesh, noted that the foundation concreting would soon begin at Unit 2. Pursuant to the tripartite memorandum on cooperation between Russia, Bangladesh and India, 50 young Bangladeshi engineers, who will later work at Rooppur, will be sent to India for training, he said. Other 125 students will be trained in Russia.

The Rooppur nuclear power plant will have two VVER-1200 reactor units. The construction contract was signed in December 2015.